2727909 – FAQs Related to Production Costing and Production Process

FAQs Related to Production Costing and Production Process

SAP Note này tổng hợp thông tin giải đáp các thắc mắc của người dùng liên quan đến giá thành sản xuất (Production Costing) và các vấn đề liên quan đến quy trình sản xuất (Production Process) trong hệ thống SAP Business One (SAP B1)


Symptom

You need detailed information about the production costing calculations and production processes in SAP Business One.

You have added a Receipt from Production and you wonder how the product cost has been calculated.

You have closed a Production Order (PO) and need to explain the cost of the product, or the production variance (Total Variance).

Reproducing the issue

Scenario: Frequently asked questions (FAQs)

The PDF document attached to this SAP Note contains:

  • Introduction to production master data and production quantity categories.
  • Production cost calculation principles based on the component valuation method are explained through example scenarios.
  • The following FAQs are explained:
    1. Why does production variance (Total Variance) occur? What happens to the Total Variance when you close the PO?
    2. What are the journal entry postings behind production documents?
    3. What if you add a Receipt from Production without having issued any components?
    4. What if an excess component quantity is issued?
    5. What if the component cost changes during the PO lifetime?
    6. What if the product cost estimation is performed where there is insufficient on-hand quantity of the component, or zero component quantity?
    7. Is it possible to change the product cost in order to reflect an increase in the component cost even for a closed PO?
    8. How do you add overhead costs to the PO?
    9. If a component is deleted on the PO, is there any impact on the product cost?
    10. What if you delete a component from a PO for which some quantity has already been issued?
    11. How is a returned component reflected in the product cost?
    12. How is the product cost estimated with FIFO components and multiple receipts?
    13. How does a disassembly PO set the cost of the received components?
    14. Why do disassembly POs not show the Receipt from Production in the relationship map?
    15. Does the cost of a by-product influence the product cost?
    16. What if the product is received in different warehouses or the product Warehouse is changed before the PO is closed?
    17. Does the component cost affect product cost if the product is using the standard valuation method?
    18. What if a standard-valuated product has been revaluated between two partial Receipts from Production?
    19. What if the planned quantity of the parent item changes during the PO duration?
    20. What if you reject some produced quantity?
    21. Does using route stages have an impact on product costing?
    22. What if the additional component quantity (Additional Qty) changes during the lifetime of a PO?
    23. What if you need to change the planned quantity for a backflush item?
    24. Can you cancel a PO after creating a Receipt from Production or an Issue for Production?
    25. Can you change the valuation method of a component or product during the PO lifetime?
    26. Can you change the management method of components or products between not managed items vs. serial number or batch management during the PO lifetime?
    27. What if bills of materials are redesigned during the PO lifetime?
    28. What if the same item or resource appears on more than one row of the PO?
    29. Can you process several POs or PO lines at once?
    30. How is the product cost determined in non-perpetual inventory companies?

Cause

Functionality description

Solution

Detailed explanations for the above FAQs are contained in the PDF document attached to this SAP Note.

In order to view the list of components and their cost contribution to the cost of the product item, we recommend to utilize the Variance Report (available as of SAP Business One 9.3 PL02). To run the report, in the Production Order window, on the Summary tab, click the link arrow to open the Variance Report.

Note: As soon as a receipt or issue document is created based on a PO, content data for the report exist. Then the yellow link arrow leading to the Variance Report is active, even if there is no variance.

For application versions lower than 9.3 PL02:

We recommend viewing the Production Order Relationship Map to view the documents linked to the PO. In the case of more complex POs, you may also use the following query, which will display a sorted list of all documents related to the specific PO. The oldest documents are displayed first:

select “ItemCode”, “InQty”, “OutQty”, “CalcPrice”, “TransValue”, * from oinm where “ApplObj”=’202′ and “AppObjAbs”=’XYZ‘  order by “TransNum”;

You need to replace XYZ with the OWOR.DocEntry of the production order.

Down load PDF file

Picture of Trần Văn Sơn

Trần Văn Sơn

Với 18+ năm kinh nghiệm và 50+ dự án thành công, tôi chuyên giải quyết bài toán quản trị từ gốc rễ quy trình và con người. Phương châm của tôi là hướng doanh nghiệp vận hành theo chuẩn SAP B1 toàn cầu, đảm bảo hệ thống vận hành đơn giản, hiệu quả ở hiện tại và dễ dàng nâng cấp, mở rộng trong tương lai.
Thảo luận và chia sẻ kinh nghiệm
Bạn có gặp tình huống tương tự khi sử dụng hệ thống SAP Business One?

Bài có liên quan theo chủ đề đang xem

Scroll to Top